The work on the construction of the multifunctional hall in Brno has mainly shifted indoors

Publisher
ČTK
12.01.2026 18:20

Brno - The multifunctional hall being built in the grounds of the Brno exhibition center is under roof; workers are only finishing the cladding of the canopies on the outside. All other construction activities have moved indoors, said Petr Kratochvíl (ODS), chairman of the board of the municipal company Arena Brno and councilor, to ČTK. The construction, costing approximately five billion crowns, is scheduled to open in the fall.


"Work is fully concentrated indoors, and the building is heated to allow construction to continue even in freezing weather. Currently, the load-bearing structures are completely finished, workers are working on drywall constructions and pouring floors. At the same time, they are focusing on the installation of heating, cooling, air conditioning, electrical installations, and other technical systems," Kratochvíl stated.

The construction of the municipal hall started in September 2023. The original costs were 4.4 billion crowns but have gradually increased by about half a billion. Additional hundreds of millions of crowns will be needed for the arena's equipment. The municipal company is now finalizing the selection of suppliers for the lighting of the dominant zones, information technologies, and cybersecurity, special audiovisual and stage technologies, interiors, orientation systems, and catering services.

Once completed, the building will offer 30 different types of use, have a capacity of up to 13,000 spectators, and 1,300 parking spaces. Around 100 events are expected to be held there annually. Over 60 percent of the program will consist of concerts featuring Czech and world music names, family shows, and other cultural events. A significant portion will be dedicated to sports. The arena will be home to the Kometa Brno hockey club.
The English translation is powered by AI tool. Switch to Czech to view the original text source.
0 comments
add comment

Related articles

0 26.12.2025 | In Brno, they will open a multifunctional hall next year
0 22.10.2025 | The multifunctional hall at the Brno Exhibition Center will open next fall
0 07.08.2024 | The additional work increased the cost of building the hall at the Brno exhibition center by 19 million crowns
0 18.09.2023 | Construction of a multifunctional hall worth nearly six billion has begun at the Brno exhibition center
0 18.09.2023 | Brno will start the construction of a multifunctional hall for nearly six billion crowns
0 16.01.2023 | Brno has signed a contract for the construction of a multifunctional hall at the exhibition grounds for 4.4 billion
0 09.05.2022 | The council of Brno approved a new concession procedure for the operator of the multifunctional hall
0 28.04.2022 | Brno did not reach an agreement with Kometa on the operation of the planned multifunctional hall
0 23.03.2022 | Brno is exhibiting models of the planned multifunctional hall at Vaňkovka
0 22.03.2022 | Brno will receive a grant from the National Sports Agency for the construction of a multifunctional hall
2 01.12.2021 | Brno is looking for a company to build a multifunctional hall at a cost of up to four billion
0 04.08.2021 | Brno has obtained a billion-dollar loan for the construction of a multifunctional hall at the exhibition grounds
1 29.06.2021 | The demolition of buildings has begun at the Brno exhibition center, making way for the construction of an arena
0 21.06.2021 | Multifunctional hall in Brno has received a zoning decision and building permit
1 17.06.2021 | South Moravian Region will allocate at least 200 million for the construction of a multifunctional hall in Brno
0 17.06.2021 | In the planned multifunctional hall in Brno, 688 parking spaces will be created
0 21.04.2021 | Due to the construction of a multifunctional hall in Brno, 21 buildings are awaiting demolition in the coming months
1 03.02.2021 | Brno is searching for an operator for the planned multipurpose hall for 2.5 billion.
0 02.12.2020 | Brno is looking for a company to demolish buildings on the site for a multifunctional hall
0 28.08.2020 | Brno has requested an EIA opinion for the construction of a multifunctional hall
0 24.10.2019 | Brno has a contractor for the construction documentation of the multifunctional hall
0 22.09.2019 | Brno is preparing a multifunctional hall at the exhibition grounds, another one is planned in Vodova
0 20.03.2019 | Brno and the region agreed with the state to support the construction of a hall for Kometa
0 20.02.2019 | The Hall of the Comets will not be in Brno at the velodrome site, but at Pavilion Z
0 26.09.2018 | Brno has memoranda for the construction of a velodrome and a hall for the Komet's hockey players
0 23.04.2018 | The hockey hall for Kometa for 1.4 billion will be built at the exhibition center